FJW-2026-016 · Staircase

The Abrahams Residence

Balustrade and handrail upgrade

In Production22d (over threshold)

Order value excl. VAT

R125,000

Assigned to

Reza Patel

Since enquiry

52 days

Recorded activity

16 events

Order journey

Step 7 of 10
  1. Enquiry

  2. Costing & Quote

  3. Quote Approved

  4. Deposit Received

  5. Measure & Drawings

  6. Production Planning

  7. 7

    In Production

  8. 8

    Quality Check

  9. 9

    Ready & Invoiced

  10. 10

    Delivered / Installed

3 November 2026

3 events

  1. Note

    Hinges back-ordered, supplier confirmed ETA.

    Order timeline

  2. Site visit

    Checked site access and noted the measurement team's arrival arrangements.

    Contact: Kabelo (demo)

    Reza Patel

  3. Follow-up added

    Confirm the revised dimensions with the site contact.

    Due 14 Nov 2026, 09:00

    Lindiwe October

23 October 2026

1 event

  1. Stage

    Moved from Production Planning to In Production

    5 days in the previous stage

    Order timeline

21 October 2026

1 event

  1. Note

    Architect drawings received, revision B.

    Order timeline

18 October 2026

1 event

  1. Stage

    Moved from Measure & Drawings to Production Planning

    6 days in the previous stage

    Order timeline

12 October 2026

1 event

  1. Stage

    Moved from Deposit Received to Measure & Drawings

    4 days in the previous stage

    Order timeline

8 October 2026

2 events

  1. Stage

    Moved from Quote Approved to Deposit Received

    6 days in the previous stage

    Order timeline

  2. Deposit

    Deposit received: R62,500 (50%)

    Order timeline

2 October 2026

2 events

  1. Stage

    Moved from Costing & Quote to Quote Approved

    7 days in the previous stage

    Order timeline

  2. Approved

    Client approved quote

    Order timeline

29 September 2026

2 events

  1. Quote

    Quote sent: R125,000 excl. VAT

    Order timeline

  2. Quote

    Quote FJW-2026-016.pdf

    Reza Patel

25 September 2026

1 event

  1. Stage

    Moved from Enquiry to Costing & Quote

    2 days in the previous stage

    Order timeline

24 September 2026

1 event

  1. Assigned

    Assigned to Reza Patel

    Order timeline

23 September 2026

1 event

  1. Created

    Enquiry received via phone

    Order timeline